Crowded first passenger train celebrates inside Auckland's new underground City Rail Link tunnel

Auckland Opens $5.4B Rail Tunnel After 100-Year Wait

😊 Feel Good

At 4:57am on a Sunday morning, the first passenger train rolled through Auckland's new underground rail tunnels, ending a century-long dream. Passengers chanted "tunnel, tunnel, tunnel" as they made history on New Zealand's largest transport project ever.

After more than 100 years of planning and a decade of construction, Auckland's City Rail Link finally welcomed its first passengers with cheers, chants, and pure joy at 4:57am on Sunday morning.

Around 150 eager train enthusiasts lined up at Ōtāhuhu Station, some arriving as early as 4:10am to claim their spot on history. The carriages filled with dignitaries, council staff, and excited locals who had waited years to see this moment arrive.

As the train entered the new tunnel, passengers broke into spontaneous chants of "tunnel, tunnel, tunnel" and erupted in cheers when it pulled into Karanga-a-Hape station. One passenger told reporters the experience earned an "A plus" and exceeded all expectations.

The $5.4 billion project connects two new 3.5km rail tunnels through Auckland's city center, linking the existing network with two brand new CBD stations near Karangahape Road and Aotea Square. Construction finally began in 2015 after the idea had been discussed, debated, and shelved repeatedly since the 1920s.

The journey to this day spans generations of leadership. Railways Minister Gordon Coates first proposed an underground rail link in the 1920s, followed by Mayor Dove-Myer Robinson's rapid rail vision in the 1960s and 70s.

Auckland Opens $5.4B Rail Tunnel After 100-Year Wait

Mayor Len Brown finally made the tunnel a centerpiece of his 2010 election campaign and pushed it across the finish line by convincing the national government to back the ambitious project. What had seemed impossible for a century became reality through decades of persistence.

The Ripple Effect

The transformation goes far beyond a celebratory first ride. Auckland Council expects the CRL to double the number of people who can reach the city center by public transport within 30 minutes.

Travel times across the network will drop significantly while train frequency increases, bringing thousands more people into the CBD each day. Peak train capacity will jump by at least 50 percent, fundamentally changing how Auckland moves.

KiwiRail spent five years upgrading the wider rail network to handle the increased demand, rebuilding old track foundations and improving drainage systems. The agency says full network closures are now a thing of the past.

For a city long dependent on cars and plagued by congestion, the CRL represents a fundamental shift toward sustainable urban transport. The project proves that even century-old dreams can come true with enough determination and collective vision.

More Images

Auckland Opens $5.4B Rail Tunnel After 100-Year Wait - Image 2
Auckland Opens $5.4B Rail Tunnel After 100-Year Wait - Image 3
Auckland Opens $5.4B Rail Tunnel After 100-Year Wait - Image 4
Auckland Opens $5.4B Rail Tunnel After 100-Year Wait - Image 5

Based on reporting by Stuff NZ

This story was written by BrightWire based on verified news reports.